RJ Scaringe has sent out emails to order holders announcing that deliveries have been pushed back to September.

"Earlier this summer we announced that deliveries would begin in July; however, the timing of the first deliveries of the R1T has shifted to September, with the R1S shortly thereafter in the fall. I wanted to be sure you heard this from me directly.

There are many reasons why our production ramp is taking longer than expected. The cascading impacts of the pandemic have a compounding effect greater than anyone has anticipated. Everything from facility construction, to equipment installation, to vehicle component supply (especially semiconductors) has been impacted by the pandemic. Beyond these unforeseen challenges, launching three new vehicles while setting up a multi-vehicle manufacturing plant is a complex orchestra of coordinated and interlinked activities where small issues can translate into ramp delays."